Project Charter
Problem and Overall Solution
Requirements Table
Budget
Risk Analysis (TODO)
Tasks And Gantt Diagram
Deliverables
Deliverable 1
Members (Group 3)
Guilherme Correa Koller (Manager)
Daniel Augusto Pires de Castro
Mateus Filipe de Ornelas Rampim
Pedro Henrique Fracaro Kiche
Thaís Say de Carvalho
Victor Gabriel Almeida e Almeida
Videos Link
Preliminary List of Deliveries (Weekly)
Deliverable 1: Mechanical Assembly – 50%
- Structure of the XY table partially assembled (rails, frame)
- First axis motion tested with manual positioning
- Initial mounting of robot (non-functional prototype)
Deliverable 2: Mechanical Assembly – 100%
- Complete XY table movement structure (with belts, pulleys, and mounts)
- Mounting of puppet with articulated limbs
- Endstop switches mechanically installed
Deliverable 3: Electronics – 100% / Software – 50%
- Wiring and power distribution fully installed
- Stepper and servo motor drivers connected and functional
- Raspberry Pi controlling basic movement (test scripts)